2019-2024: The Rise of Green Intelligent Manufacturing
                       -	In March 2019, it was listed as a key construction project in Guangdong Province, accelerating the construction of environmental protection infrastructure.
- In August 2021, the first batch of electroplating enterprises went into production, and the supporting wastewater treatment plant began construction, achieving "production-environmental protection" integration.
- In January 2023, the largest and most technologically advanced wastewater treatment plant in Shanwei was completed, treating 5,600 tons of wastewater daily using international-level processes such as ultrafiltration devices, activated carbon filtration, and constructed wetlands to ensure zero pollution discharge.
- In April 2024, the wastewater treatment plant was fully operational, and all six functional areas of the cluster (processing plant area, electroplating production area, wastewater treatment area, etc.) were fully activated, forming a closed-loop "R&D-design-production-environmental protection-logistics" industrial chain.